Project: Phenolic Floral Foam Production Line (Resin Synthesis & Manual Foaming)
Destination:
Notice to Buyer: To ensure smooth installation, safe operation, and timely commissioning by our engineers, please complete and verify all items below at least 15 days prior to our engineers’ departure. Please check [✓] when completed and attach photos/videos for verification.
1. Workshop Infrastructure & Sri Lanka Climate Adaptation
- [ ] Ceiling Height & Space: Minimum 5.5 meters clear height in the Resin Reactor area (for condenser and overhead tanks). At least 300 m² well-ventilated area for manual foaming and cutting, separated from the reactor room.
- [ ] Acid-Proof Flooring & Bunding: Floor in the reactor, acid-mixing, and foaming areas must be coated with ≥3mm heavy-duty acid/alkali-resistant epoxy (or acid-proof tiles). A 10–15 cm containment bund (curb) must be built around the chemical area to prevent spills from leaking outside.
- [ ] Explosion-Proof (Ex-Rated) Zone: All lighting, switches, and exhaust fans in the Phenol/Formalin storage and reactor zones must be Explosion-Proof. Grounding (anti-static) wires must be properly installed. Strictly NO open flames.
- [ ] Temperature Control (Crucial for Sri Lanka Climate): Due to high ambient temperatures (28°C–35°C+), an industrial air conditioner or chiller room MUST be installed for the resin/blowing agent storage and foaming room to keep raw materials at 15°C–20°C before foaming.
2. Utilities (Power, Heating, Cooling, Air)
- [ ] Power Supply: 400V / 50Hz, 3-Phase, 5-Wire industrial power connected to the main distribution cabinet next to the machines. Voltage stabilizer is strongly recommended.
- [ ] Heating Source: Thermal oil boiler or steam boiler installed, pressure-tested, and piped directly to the reactor jacket inlet/outlet.
- [ ] Cooling Water System: Cooling tower (water tank capacity 3–5 times the reactor volume) and circulating water pump installed and piped to the reactor condenser and jacket.
- [ ] Compressed Air: Air compressor (0.6–0.8 MPa), air receiver tank, and air dryer installed with air lines routed to pneumatic valves and cleaning stations.
3. On-Site Installation Tools & Lifting Equipment (Prepared by Buyer)
- [ ] Lifting & Handling: Forklift (≥ 3 Tons capacity), manual hydraulic pallet truck, lifting slings, and chain blocks (for erecting the reactor).
- [ ] Installation Tools: Electric welding machine, angle grinder, impact drill, pipe wrenches, spanner sets, and ladders (≥ 4 meters).
- [ ] Consumables: Expansion bolts, Teflon tape, acid-resistant silicone sealant, gear oil for reducers, and high-temperature grease.
4. Environmental Protection & Safety Equipment (Mandatory Before Startup)
- [ ] Exhaust Scrubber System: Exhaust hoods installed above the reactor manhole and foaming area, connected to an Alkaline Spray Scrubber Tower + Activated Carbon Box to neutralize phenol, formaldehyde, and acid fumes (compliant with Sri Lanka CEA standards).
- [ ] Dust Collector: Bag-type dust collector connected to the floral foam cutting machine to capture fine acidic phenolic dust.
- [ ] Emergency Eyewash & Shower: Combination emergency safety shower and eyewash station installed within 5 meters of the reactor and acid-mixing station, connected to clean running water.
- [ ] Firefighting & Neutralizer: Dry powder and CO₂ fire extinguishers placed every 50 m². At least 50 kg of Sodium Bicarbonate (Baking Soda) kept on-site for emergency acid spill neutralization.
- [ ] Personal Protective Equipment (PPE) for Operators:
- Full-face gas masks with Organic Vapor cartridges (for Phenol/Formalin) and Acid Gas cartridges (for curing acid).
- Heavy-duty acid-resistant chemical coveralls/aprons.
- Long-cuff Nitrile or Neoprene acid-resistant gloves.
- Acid-resistant steel-toe safety boots.
- N95/KN95 dust masks and safety goggles for cutting operators.
5. Raw Materials for Trial Run (Ready On-Site)
- [ ] Resin Synthesis: Industrial Phenol, Formaldehyde solution (37%), Alkaline catalyst (NaOH/KOH), Acid neutralizer (Formic/Acetic/Phosphoric acid).
- [ ] Foaming & Curing: Foaming-grade phenolic resin (if testing foaming first), Silicone surfactant, Low-boiling blowing agent (e.g., Pentane), Acidic curing agent (Sulfonic acid blend), Acid-resistant green pigment, Wetting agent, Mold release agent.
Buyer Confirmation & Signature:
We confirm that all items checked above are completed and ready for installation and commissioning.
Company Name: ___________________________
Authorized Representative: ___________________
Signature & Stamp: _______________________
Date: ___________________________________